When you change the start or end date of an existing project from an undetermined date to a real date, the project may shift as the new position of weekends, off-days, and other exceptions are taken into account. For example, “T+2w 1d” means 2 weeks and 1 day after the start of the project. In a project with an undetermined date, all dates are represented in the format “T day”, for the first day of the project, or “T + x”, where x is some time duration. The normal work week for the project and for the individual resources is respected, but work schedule exceptions such as holidays are ignored. For the purposes of applying the work week, the project is assumed to start on the first day of the week. If you don’t know when the project will start or end, you can mark the start date undetermined in the Project Information inspector. While tasks in most projects are scheduled for completion as soon as possible, it can be helpful to plan a project with a defined "ship date" from that date backward to help determine when work on it should begin. ![]() ![]() Changing the direction of individual tasks is covered in the Task Schedule Inspector section. In the former case all tasks in the project are scheduled for completion as soon as possible (ASAP), while in the latter case all tasks are scheduled as late as possible (ALAP). ![]() Setting a project's start or end date defines the project's direction: whether the schedule is built forward from a start date, or backward from an end date.
0 Comments
Leave a Reply. |
AuthorWrite something about yourself. No need to be fancy, just an overview. ArchivesCategories |